Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors

Specifications & Public Works Accounts MCQs

1. Which of the following accurately describes the importance of specifications in construction projects?

a) Specifications ensure that projects are completed within budget
b) Specifications guarantee the quality of materials used
c) Specifications provide detailed instructions for construction
d) Specifications primarily focus on project aesthetics

Answer: c) Specifications provide detailed instructions for construction

Explanation: Specifications are crucial documents in construction projects as they outline the standards, materials, and methods to be used, ensuring clarity and consistency in execution.

2. What are the main types of specifications used in construction?

a) Technical, budgetary, and aesthetic
b) Performance, proprietary, and reference standard
c) General, specific, and financial
d) Architectural, engineering, and environmental

Answer: b) Performance, proprietary, and reference standard

Explanation: Performance specifications describe desired outcomes, proprietary specifications specify particular brands or products, and reference standard specifications refer to existing industry standards.

3. Which type of specification specifies a particular brand or product to be used in construction?

a) Performance
b) Reference standard
c) Proprietary
d) Technical

Answer: c) Proprietary

Explanation: Proprietary specifications dictate the use of specific brands or products, limiting choices to those specified.

4. In construction, what is the purpose of a measurement book?

a) To record the measurements of completed structures
b) To document the dimensions of materials on-site
c) To track the progress of construction activities
d) To record the quantity of materials used in a project

Answer: d) To record the quantity of materials used in a project

Explanation: A measurement book is used to record the quantity and description of materials used in construction, facilitating accurate billing and inventory management.

5. Which account is used to track the expenses related to tools and equipment used in construction projects?

a) Cash book
b) Materials at site account
c) Tools and plants account
d) Imprest account

Answer: c) Tools and plants account

Explanation: The tools and plants account is specifically used to track expenses related to tools and equipment used in construction projects.

6. What is the purpose of a cash book in construction accounting?

a) To record transactions related to materials purchases
b) To track the cash flow of a construction project
c) To document payments made to subcontractors
d) To record expenses for labor

Answer: b) To track the cash flow of a construction project

Explanation: A cash book is used to record all cash transactions, including receipts and payments, providing a clear overview of the project’s cash flow.

7. Which document is used to request payment for work completed at various stages of a construction project?

a) Final bill
b) Secured advance
c) Running bill
d) Imprest account

Answer: c) Running bill

Explanation: Running bills are interim invoices submitted by contractors to request payment for work completed at different stages of a construction project.

8. What is the purpose of an imprest account in construction management?

a) To maintain a reserve of funds for emergencies
b) To manage petty cash expenses
c) To track subcontractor payments
d) To provide advances to laborers

Answer: b) To manage petty cash expenses

Explanation: An imprest account is used to manage petty cash expenses, providing a convenient way to cover small, day-to-day costs on a construction site.

9. Which account is used to record materials stored at the construction site but not yet used in the project?

a) Cash book
b) Materials at site account
c) Imprest account
d) Tools and plants account

Answer: b) Materials at site account

Explanation: The materials at site account is used to record materials stored at the construction site until they are used in the project, helping to track inventory and prevent shortages.

10. What is the purpose of a final bill in construction projects?

a) To request payment for completed work at the end of the project
b) To document the total cost of materials used
c) To track expenses for tools and equipment
d) To reconcile discrepancies in the project budget

Answer: a) To request payment for completed work at the end of the project

Explanation: A final bill is submitted by the contractor to request payment for all completed work at the conclusion of a construction project, ensuring all expenses are accounted for before project closure.

Leave a Comment